Based on our performance with other projects with this client, RINER was selected as the Construction Materials Testing firm for this 12-story office building and 6-level parking garage development project. The building was founded on spread footings and the overall design included cast in place concrete decks and columns with post-tension reinforced beams.
RINER testing and inspection scope included earthwork for the building pad, garage pad, paving, and public and private utilities. Onsite soils and available borrow materials were of varying quality which required continuous monitoring to ensure that out of specification materials were not placed within the building pad area.
The testing and inspection scope for the building and garage also included mild and post-tension reinforcing steel, concrete and structural steel.